30 C.F.R. § 285.631

Current through November 30, 2024
Section 285.631 - When must I initiate activities under an approved COP?

After your COP is approved, you must commence construction by the date given in the construction schedule required by 30 CFR 585.626(b)(21) , and included as a part of your approved COP, unless BOEM approves a deviation from your schedule.

30 C.F.R. §285.631

88 FR 6413 , 1/31/2023