Section 250.867 - Temporary quarters and temporary equipment
(a) You must equip temporary quarters with all safety devices required by API RP 14C, Appendix C (incorporated by reference as specified in § 250.198 ). The District Manager must approve the safety system/safety devices associated with the temporary quarters prior to installation.
(b) The District Manager may require you to install a temporary firewater system for temporary quarters in production processing areas or other classified areas.
(c) Temporary equipment associated with the production process system, including equipment used for well testing and/or well clean-up, must be approved by the District Manager.
(d) The District Manager must approve temporary generators that would require a change to the electrical one-line diagram in § 250.842(a) .

30 C.F.R. §250.867

81 FR 60918, Sept. 7, 2016, as amended at 83 FR 49259, Sept. 28, 2018