When you . . . | Then you must . . . | And . . . |
(1) Intend to revise your drilling plan, change major drilling equipment, or plugback, | Submit form BSEE-0124 or request oral approval, | Receive written or oral approval from the District Manager before you begin the intended operation. If you get an approval, you must submit form BSEE-0124 no later than the end of the 3rd business day following the oral approval. In all cases, or you must meet the additional requirements in paragraph (b) of this section. |
(2) Determine a well's final surface location, water depth, and the rotary kelly bushing elevation, | Immediately Submit a form BSEE-0124, | Submit a plat certified by a registered land surveyor that meets the requirements of § 250.412 . |
(3) Move a drilling unit from a wellbore before completing a well, | Submit forms BSEE-0124 and BSEE-0125 within 30 days after the suspension of wellbore operations, | Submit appropriate copies of the well records. |
30 C.F.R. §250.465