You must submit reports to us as indicated in the following table. Sections 203.81 , 203.90 , and 203.91 describe what these reports must include. The BSEE Regional Office for your region will prescribe the formats.
Required report | When due to BSEE | Due date extensions |
(a) Fabricator's confirmation report. | Within 18 months after approval of relief. | BSEE Director may grant you an extension under § 203.79(c) for up to 6 months. |
(b) Post-production report. | Within 120 days after the start of production that is subject to the approved royalty suspension volume. | With acceptable justification from you, the BSEE Regional Director for your region may extend the due date up to 30 days. |
30 C.F.R. §203.70