29 C.F.R. § 97.51

Current through May 31, 2024
Section 97.51 - Later disallowances and adjustments

The closeout of a grant does not affect:

(a) The Federal agency's right to disallow costs and recover funds on the basis of a later audit or other review;
(b) The grantee's obligation to return any funds due as a result of later refunds, corrections, or other transactions;
(c) Records retention as required in § 97.42 ;
(d) Property management requirements in §§ 97.31 and 97.32 ; and
(e) Audit requirements in § 97.26 .

29 C.F.R. §97.51