24 C.F.R. § 245.419

Current through May 31, 2024
Section 245.419 - Initial submission of materials to HUD: Major capital additions

In the case of major capital additions, the mortgagor must submit the following materials to the local HUD office:

(a) The general plans and sketches of the proposed capital additions;
(b) A statement describing the estimated effect of the proposed capital additions on the value of the project, the project income and expenses (including property taxes), and the project rent schedule;
(c) A statement describing how the proposed capital additions will be financed and the effect, if any, of that financing on the tenants;
(d) A statement assessing the compatibility of the proposed capital additions with the residential character of the project; and
(e) A copy of the notice to tenants.

24 C.F.R. § 245.419

Approved by the Office of Management and Budget under control number 2502-0310