23 C.F.R. § 661.51

Current through May 31, 2024
Section 661.51 - Can IRRBP funds be used for the approach roadway to a bridge?
(a) Yes, costs associated with approach roadway work, as defined in § 661.5 are eligible.
(b) Long approach fills, causeways, connecting roadways, interchanges, ramps, and other extensive earth structures, when constructed beyond an attainable touchdown point, are not eligible uses of IRRBP funds.

23 C.F.R. §661.51