23 C.F.R. § 140.907

Current through May 31, 2024
Section 140.907 - Overhead and indirect construction costs
(a) A State may elect to reimburse the railroad company for its overhead and indirect construction costs.
(b) The FHWA will participate in these costs provided that:
(1) The costs are distributed to all applicable work orders and other functions on an equitable and uniform basis in accordance with generally accepted accounting principles;
(2) The costs included in the distribution are limited to costs actually incurred by the railroad;
(3) The costs are eligible in accordance with the Federal Acquisition Regulation (48 CFR), part 31, Contract Cost Principles and Procedures, relating to contracts with commercial organizations;
(4) The costs are considered reasonable;
(5) Records are readily available at a single location which adequately support the costs included in the distribution, the method used for distributing the costs, and the basis for determining additive rates;
(6) The rates are adjusted at least annually taking into consideration any overrecovery or underrecovery of costs; and
(7) The railroad maintains written procedures which assure proper control and distribution of the overhead and indirect construction costs.

23 C.F.R. §140.907

53 FR 18276, May 23, 1988