18 C.F.R. § 381.303

Current through September 30, 2024
Section 381.303 - Review of a Department of Energy remedial order
(a) Except as provided in § 381.303(b) , the fee established for an answer to a Department of Energy remedial order under subpart I of the Commission's Rules of Practice and Procedure, 18 CFR part 385 , subpart I (1983), is $55,120. The fee must be submitted in accordance with subpart A of this part.
(b) If the amount in controversy is below $30,000, then the fee to file a petition for review of a DOE remedial order is reduced as follows:

Fee
Amount in controversy:
$0 to $9,999$100
$10,000 to $29,999600

(c) In order to qualify for the fees in paragraph (b) of this section, the check must be accompanied by an affidavit by the petitioner that states the amount in controversy.

18 C.F.R. §381.303

Order 395, 49 FR 35356, Sept. 7, 1984
81 FR 2749, 1/19/2016; 82 FR 9129, 3/6/2017; 83 FR 469, 2/5/2018; 84 FR 14260, 5/10/2019; 85 FR 1103, 2/10/2020; 86 FR 11425, 3/29/2021; 87 FR 5660, 3/4/2022; 88 FR 6165, 3/2/2023; 89 FR 1034, 2/8/2024