18 C.F.R. § 284.6

Current through April 30, 2024
Section 284.6 - Rate interpretations
(a)Procedure. A pipeline may obtain an interpretation pursuant to subpart L of part 385 of this chapter concerning whether particular rates and charges comply with the requirements of this part.
(b)Address. Requests for interpretations should be addressed to: FERC Part 284 Interpretations, Office of General Counsel, Federal Energy Regulatory Commission, Washington, DC 20426.

18 C.F.R. §284.6

44 FR 66791, Nov. 21, 1979; 44 FR 75383, Dec. 20, 1979, as amended by Order 225, 47 FR 19058, May 3, 1982; Order 581, 60 FR 53072, Oct. 11, 1995
44 FR 66791, 11/21/1979; 44 FR 75383, 12/20/1979, as amended by Order 225, 47 FR 19058, 5/3/1982; Order 581, 60 FR 53072, 10/11/1995