18 C.F.R. § 157.38

Current through April 30, 2024
Section 157.38 - Pre-approval procedures

No later than 90 days prior to providing the notice of open season required by § 157.34(a) , a prospective applicant must file, for Commission approval, a detailed plan for conducting an open season in conformance with this subpart. The prospective applicant's plan shall include the proposed notice of open season. Upon receipt of a request for such a determination, the Secretary of the Commission shall issue a notice of the request, which will then be published in the FEDERAL REGISTER. The notice shall establish a date on which comments from interested persons are due and a date, which shall be within 60 days of receipt of the prospective applicant's request unless otherwise directed by the Commission, by which the Commission will act on the proposed plan.

18 C.F.R. §157.38

Order 2005-A, 70 FR 35026, June 16, 2005