18 C.F.R. § 5.14

Current through November 30, 2024
Section 5.14 - Formal study dispute resolution process
(a) Within 20 days of the Study Plan Determination, any Federal agency with authority to provide mandatory conditions on a license pursuant to FPA Section 4(e), 16 U.S.C. 797(e) , or to prescribe fishways pursuant to FPA Section 18, 16 U.S.C. 811 , or any agency or Indian tribe with authority to issue a water quality certification for the project license under section 401 of the Clean Water Act, 42 U.S.C. 1341 , may file a notice of study dispute with respect to studies pertaining directly to the exercise of their authorities under sections 4(e) and 18 of the Federal Power Act or section 401 of the Clean Water Act.
(b) The notice of study dispute must explain how the disputing agency's or Indian tribe's study request satisfies the criteria set forth in § 5.9(b) , and shall identify and provide contact information for the panel member designated by the disputing agency or Indian tribe, as discussed in paragraph (d) of this section.
(c) Studies and portions of study plans approved in the Study Plan Determination that are not the subject of a notice of dispute shall be deemed to be approved, and the potential applicant shall proceed with those studies or portions thereof.
(d) Within 20 days of a notice of study dispute, the Commission will convene one or more three-person Dispute Resolution Panels, as appropriate to the circumstances of each proceeding. Each such panel will consist of:
(1) A person from the Commission staff who is not otherwise involved in the proceeding, and who shall serve as the panel chair;
(2) One person designated by the Federal or state agency or Indian tribe that filed the notice of dispute who is not otherwise involved in the proceeding; and
(3) A third person selected by the other two panelists from a pre-established list of persons with expertise in the resource area. The two panelists shall make every reasonable effort to select the third panel member. If however no third panel member has been selected by the other two panelists within 15 days, an appropriate third panel member will be selected at random from the list of technical experts maintained by the Commission.
(e) If more than one agency or Indian tribe files a notice of dispute with respect to the decision in the preliminary determination on any information-gathering or study request, the disputing agencies or Indian tribes must select one person to represent their interests on the panel.
(f) The list of persons available to serve as a third panel member will be posted, as revised from time-to-time, on the hydroelectric page of the Commission's Web site. A person on the list who is requested and willing to serve with respect to a specific dispute will be required to file with the Commission at that time a current statement of their qualifications, a statement that they have had no prior involvement with the proceeding in which the dispute has arisen, or other financial or other conflict of interest.
(g) All costs of the panel members representing the Commission staff and the agency or Indian tribe which filed the notice of dispute will be borne by the Commission or the agency or Indian tribe, as applicable. The third panel member will serve without compensation, except for certain allowable travel expenses as defined in 31 CFR part 301.
(h) To facilitate the delivery of information to the dispute resolution panel, the identity of the panel members and their addresses for personal service with respect to a specific dispute resolution will be posted on the hydroelectric page of the Commission's Web site.
(i) No later than 25 days following the notice of study dispute, the potential applicant may file with the Commission and serve upon the panel members comments and information regarding the dispute.
(j) Prior to engaging in deliberative meetings, the panel shall hold a technical conference for the purpose of clarifying the matters in dispute with reference to the study criteria. The technical conference shall be chaired by the Commission staff member of the panel. It shall be open to all participants, and the panel shall receive information from the participants as it deems appropriate.
(k) No later than 50 days following the notice of study dispute, the panel shall make and deliver to the Director of the Office of Energy Projects a finding, with respect to each information or study request in dispute, concerning the extent to which each criteria set forth in § 5.9(b) is met or not met, and why, and make recommendations regarding the disputed study request based on its findings. The panel's findings and recommendations must be based on the record in the proceeding. The panel shall file with its findings and recommendations all of the materials received by the panel. Any recommendation for the potential applicant to provide information or a study must include the technical specifications, including data acquisition techniques and methodologies.
(l) No later than 70 days from the date of filing of the notice of study dispute, the Director of the Office of Energy Projects will review and consider the recommendations of the panel, and will issue a written determination. The Director's determination will be made with reference to the study criteria set forth in § 5.9(b) and any applicable law or Commission policies and practices, will take into account the technical expertise of the panel, and will explain why any panel recommendation was rejected, if applicable. The Director's determination shall constitute an amendment to the approved study plan.

18 C.F.R. §5.14