This part implements section 30(a) of the Federal Power Act, as amended, and provides procedures for obtaining a determination from the Commission that the facility to be constructed is a qualifying conduit hydropower facility, as defined in § 4.30(b)(26) , and thus, is not required to be licensed under Part I of the FPA.
18 C.F.R. §4.400