(1) 28 gauge sheet metal on 1/4 -inch asbestos mill board or equivalent.......................... | ..........................12 inches |
(2) 28 gauge sheet metal on 1/8 -inch asbestos mill board spaced out one-inch on noncombustible spacers or equivalent.......................... | ..........................9 inches |
(3) 22 gauge sheet metal on 1-inch rockwool bats reinforced with wire mesh or the equivalent.......................... | ..........................3 inches |
(4) Where ducts are protected with an approved automatic sprinkler system, properly maintained; the clearance may be reduced to 6 inches. |
Cal. Code Regs. Tit. 8, § 5450
2. Amendment of subsections (b), (c) and (k) filed 12-5-86; effective thirtieth day thereafter (Register 86, No. 51).
Note: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code.
2. Amendment of subsections (b), (c) and (k) filed 12-5-86; effective thirtieth day thereafter (Register 86, No. 51).