In addition to the requirements in Section 8391, the employer also shall ensure that each working surface:
(a) Is cleared of tools, materials, and equipment that are not necessary to perform the job in progress;(b) Is cleared of debris, including solid and liquid wastes, at the end of each work shift or job, whichever occurs first;(c) Is maintained, so far as practicable, in a dry condition. When a wet process is used, the employer shall maintain drainage and provide false floors, platforms, mats, or other dry standing places.Cal. Code Regs. Tit. 8, § 8391.2
1. New section filed 12-13-2011; operative 12-13-2011. Submitted to OAL for printing only pursuant to Labor Code section 142.3(a)(3) (Register 2011, No. 50). Note: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code.
1. New section filed 12-13-2011; operative 12-13-2011. Submitted to OAL for printing only pursuant to Labor Code section 142.3(a)(3) (Register 2011, No. 50).