Cal. Code Regs. tit. 4 § 7415

Current through Register 2024 Notice Reg. No. 36, September 6, 2024
Section 7415 - Eligible Project Costs
(a) Eligible costs for Projects include:
(1) Facility acquisition.
(2) Renovation, including costs of:
(A) Project planning or Project management.
(B) Appraisals.
(C) Inspections.
(D) Pre-renovation, including but not limited to permit fees, surveying, architectural, and engineering fees.
(E) Hardscaping and/or landscaping essential to the completion of the Project, not to exceed 5% of total Grant award.
(3) Furnishings and/or equipment.
(4) Information technology hardware and software, not to exceed 3% of total Grant award except when approved by the Authority and only upon submission of justification that the additional information technology costs are necessary for the Project to achieve the desired goals and outcomes set forth in Section 7419, subdivision (a)(3).
(5) Up to three months of Program startup or expansion costs consisting of training, personnel salaries, and personnel benefits.
(b) Grant funds shall be used only for costs directly related to and essential for the completion of the Project.
(c) Eligible costs include only those incurred during the Grant Period.

Cal. Code Regs. Tit. 4, § 7415

1. New section filed 11-26-2018 as an emergency; operative 11-26-2018 (Register 2018, No. 48). A Certificate of Compliance must be transmitted to OAL by 5-28-2019 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 5-28-2019 as an emergency; operative 5-28-2019 (Register 2019, No. 22). A Certificate of Compliance must be transmitted to OAL by 8-26-2019 or emergency language will be repealed by operation of law on the following day.
3. Certificate of Compliance as to 5-28-2019 order transmitted to OAL 8-21-2019 and filed 10-3-2019 (Register 2019, No. 40).

Note: Authority cited: Section 5848.51, Welfare and Institutions Code. Reference: Section 5848.51, Welfare and Institutions Code.

1. New section filed 11-26-2018 as an emergency; operative 11/26/2018 (Register 2018, No. 48). A Certificate of Compliance must be transmitted to OAL by 5-28-2019 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 5-28-2019 as an emergency; operative 5/28/2019 (Register 2019, No. 22). A Certificate of Compliance must be transmitted to OAL by 8-26-2019 or emergency language will be repealed by operation of law on the following day.
3. Certificate of Compliance as to 5-28-2019 order transmitted to OAL 8-21-2019 and filed 10/3/2019 (Register 2019, No. 40).