Section 7048 - Completion of Grant Funded Project(a) The Grantee shall certify to the Authority that the Project is complete and, to the extent not already provided to the Authority, provide supporting documentation to the satisfaction of the Authority staff as follows: (1) Construction projects (including Projects with architect, design and engineering fees) require documentation including, but not limited to, copies of the certificate of occupancy and/or notice of completion. Purchase orders, invocies, and cancelled checks shall be submitted. If the Grantee does not provide copies of cancelled checks, the Grantee shall provide wire transfers, electronic fund transfers or other evidence acceptable to the Authority in lieu of copies of cancelled checks.(2) Real property acquisition Projects require a copy of the final closing statement with certification by the title company.(3) Equipment acquisition projects require service contracts, purchase orders, invoices and copies of cancelled checks to be submitted. If the Grantee does not provide copies of cancelled checks, the Grantee shall provide wire transfers, electronic fund transfers or other evidence acceptable to the Authority in lieu of copies of cancelled checks.
(b) If the Grantee fails to complete the Project within the Project Period, the Authority may require remedies, including forfeiture and return of the Grant to the Authority.(c) On a case-by-case basis, the Authority or the Authority staff may extend the Project Period for extraordinary or unavoidable delays where the Grantee can demonstrate that it occurred through no fault of its own.(d) Documentation provided to establish the completion of a Project shall clearly show that the Grant award did not exceed the cost of the Project.Cal. Code Regs. Tit. 4, § 7048
1. New section filed 2-11-2005 as an emergency; operative 2-11-2005 (Register 2005, No. 6). A Certificate of Compliance must be transmitted to OAL by 6-13-2005 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 5-26-2005 as an emergency; operative 5-26-2005 (Register 2005, No. 21). A Certificate of Compliance must be transmitted to OAL by 9-23-2005 or emergency language will be repealed by operation of law on the following day.
3. Certificate of Compliance as to 5-26-2005 order, including renumbering of former section 7048 to section 7049 and renumbering and amendment of former section 7047 to section 7048, transmitted to OAL 9-14-2005 and filed 10-27-2005 (Register 2005, No. 43).
4. Amendment of subsections (a)(1) and (a)(3) filed 10-7-2009; operative 10-7-2009 pursuant to Government Code section 11343.4 (Register 2009, No. 41). Note: Authority cited: Sections 1179.22, 1179.24 and 1179.32, Health and Safety Code. Reference: Sections 1179.22, 1179.24 and 1179.25, Health and Safety Code.
1. New section filed 2-11-2005 as an emergency; operative 2-11-2005 (Register 2005, No. 6). A Certificate of Compliance must be transmitted to OAL by 6-13-2005 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 5-26-2005 as an emergency; operative 5-26-2005 (Register 2005, No. 21). A Certificate of Compliance must be transmitted to OAL by 9-23-2005 or emergency language will be repealed by operation of law on the following day.
3. Certificate of Compliance as to 5-26-2005 order, including renumbering of former section 7048 to section 7049 and renumbering and amendment of former section 7047 to section 7048, transmitted to OAL 9-14-2005 and filed 10-27-2005 (Register 2005, No. 43).
4. Amendment of subsections (a)(1) and (a)(3) filed 10-7-2009; operative 10-7-2009 pursuant to Government Code section 11343.4 (Register 2009, No. 41).