Section 2231 - Time Schedules(a) Time schedules should be included in requirements for existing discharges when it appears that the discharger cannot immediately meet the requirements.(b) Time schedules shall not permit any unnecessary time lag, and periodic status reports should be required.(c) Time schedules should include only dates for complete design, complete financial arrangements, start of construction, 50 percent completion of work, and full compliance with requirements.(d) Time schedules should be periodically reviewed and should be updated, when necessary, to assure the most rapid compliance.Cal. Code Regs. Tit. 23, § 2231