Section 67900.1 - Purpose and Scope

This article establishes the applicable criteria and procedures for procurement, by the Department of Toxic Substances Control, of architectural and engineering services related to response actions at hazardous substance sites and corrective actions at hazardous waste facilities. These criteria and procedures shall apply to the extent such response actions are not exempted from State contract requirements under Health and Safety Code section 25358.5 or covered by Health and Safety Code section 25358.6.1 and shall be in compliance with Government Code section 19130.

Cal. Code Regs. Tit. 22, § 67900.1

1. New chapter 45.5 (article 1), article 1 (sections 67900.1-67900.12) and section filed 11-8-2001 as an emergency; operative 11-8-2001 (Register 2001, No. 45). A Certificate of Compliance must be transmitted to OAL by 3-8-2002 or emergency language will be repealed by operation of law on the following day.
2. New chapter 45.5 (article 1), article 1 (sections 67900.1-67900.12) and section refiled 3-7-2002 as an emergency; operative 3-9-2002 (Register 2002, No. 10). A Certificate of Compliance must be transmitted to OAL by 7-8-2002 or emergency language will be repealed by operation of law on the following day.
3. New chapter 45.5 (article 1), article 1 (sections 67900.1-67900.12) and section refiled 6-19-2002 as an emergency; operative 7-9-2002 (Register 2002, No. 25). A Certificate of Compliance must be transmitted to OAL by 11-6-2002 or emergency language will be repealed by operation of law on the following day.
4. Certificate of Compliance as to 6-19-2002 order, including amendment of section and NOTE, transmitted to OAL 11-6-2002 and filed 12-23-2002 (Register 2002, No. 52).

Note: Authority cited: Section 4526, Government Code. Reference: Sections 4525, 4526 and 19130, Government Code; and Sections 25358.5 and 25358.6.1, Health and Safety Code.

1. New chapter 45.5 (article 1), article 1 (sections 67900.1-67900.12) and section filed 11-8-2001 as an emergency; operative 11-8-2001 (Register 2001, No. 45). A Certificate of Compliance must be transmitted to OAL by 3-8-2002 or emergency language will be repealed by operation of law on the following day.
2. New chapter 45.5 (article 1), article 1 (sections 67900.1-67900.12) and section refiled 3-7-2002 as an emergency; operative 3-9-2002 (Register 2002, No. 10). A Certificate of Compliance must be transmitted to OAL by 7-8-2002 or emergency language will be repealed by operation of law on the following day.
3. New chapter 45.5 (article 1), article 1 (sections 67900.1-67900.12) and section refiled 6-19-2002 as an emergency; operative 7-9-2002 (Register 2002, No. 25). A Certificate of Compliance must be transmitted to OAL by 11-6-2002 or emergency language will be repealed by operation of law on the following day.
4. Certificate of Compliance as to 6-19-2002 order, including amendment of section and Note, transmitted to OAL 11-6-2002 and filed 12-23-2002 (Register 2002, No. 52).