Within 60 days of receiving a completed encroachment permit application package for broadband installation, the Department must either approve or deny the application. Upon denial of an application, a "Denial Letter" shall be sent via electronic and certified mail to the applicant clearly specifying the reasons for denial. The letter shall include the statutory or regulatory authority relied upon for denial that conflicts with the applicant's proposed plan.
Cal. Code Regs. Tit. 21, § 1412.5
Note: Authority cited: Section 671.5, Streets and Highways Code. Reference: Sections 670 and 671.5, Streets and Highways Code.