When the requested corrections have been made and/or the additional information has been provided by the responsible architect or registered engineer, an employee representative of the architect or registered engineer shall return the check set of plans and specifications along with the original plan tracings, the corrected specification pages and specification master cover sheet to the Office for backchecking. The backcheck is a comparison of the corrected plans and specifications with the check set of plans and specifications and shall be accomplished by either an Office conference between the employee representative of the architect or registered engineer and the checking engineer or by mail in the case of minor corrections to which all parties have agreed.
Changes in plans and specifications, other than changes necessary for correction,made after submission for approval, shall be brought to the attention of the Office in writing or by submission of revised plans identifying those changes clearly at the time of backchecking. Failure to give such notice automatically voids any subsequent approval given to the plans and specifications.
All requested corrections shall be made, additional requested information furnished or original design justified prior to or at the time of the backcheck. When the Office deems that the corrected plans and specifications comply with these regulations and the State Building Standards that pertain to public school construction, it shall place its stamp on the reproducible sheets of drawings and master cover sheet of the specifications. This stamp is affixed for purposes of identification only and shall not be construed as authorization to let the construction contracts. See Section 18(b). One set of prints of the stamped plans and one set of prints of the stamped specifications shall be submitted to the Office before the written approval of the application is issued.
The procedures leading to written approval of plans shall be carried to conclusion without suspension or unnecessary delay. The application shall be void where either (1) prints from corrected plans or corrected original plans are not filed for backcheck within 6 months after the date of return of checked plans to the architect or engineer, or, (2) prints of the stamped plans and one set of stamped specifications are not submitted for office files within 2 months after the date shown on the stamp of identification.
Cal. Code Regs. Tit. 21, § 18
Note: Authority cited: Sections 39152 and 81142, Education Code. Reference: Sections 39143, 39144, 39150, 81133, 81134 and 81140, Education Code.