Cal. Code Regs. tit. 14 § 15110

Current through Register 2024 Notice Reg. No. 45, November 8, 2024
Section 15110 - Projects with Federal Involvement
(a) At the request of an applicant, the lead agency may waive the one-year time limit for completing and certifying a final EIR or the 105-day period for completing a negative declaration if:
(1) The project will be subject to CEQA and to the National Environmental Policy Act,
(2) Additional time will be required to prepare a combined EIR-EIS or combined negative declaration-finding of no significant impact as provided in Section 15221, and
(3) The time required to prepare the combined document will be shorter than the time required to prepare the documents separately.
(b) The time limits for taking final action on a permit for a development project may also be waived where a combined EIR-EIS will be prepared.
(c) The time limits for processing permits for development projects under Government Code Sections 65950- 65960 shall not apply if federal statutes or regulations require time schedules which exceed the state time limits. In this event, any state agencies involved shall make a final decision on the project within the federal time limits.

Cal. Code Regs. Tit. 14, § 15110

1. Amendment of subsection (a)(2) filed 1-30-86; effective thirtieth day thereafter (Register 86, No. 5).
2. Change without regulatory effect amending NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).

Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21083.6 and 21083.7, Public Resources Code; Sections 65951 and 65954, Government Code; Public Law 91-190 as amended, 42 U.S.C.A. 4321-4347.

1. Amendment of subsection (a)(2) filed 1-30-86; effective thirtieth day thereafter (Register 86, No. 5).
2. Change without regulatory effect amendingNote filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).