With a private project, the lead agency shall complete and certify the final EIR as provided in Section 15090 within one year after the date when the lead agency accepted the application as complete. Lead agency procedures may provide that the one-year time limit may be extended once for a period of not more than 90 days upon consent of the lead agency and the applicant.
Cal. Code Regs. Tit. 14, § 15108
Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21100.2 and 21151.5, Public Resources Code; and Government Code Section 65950.