A public hearing on the LCP or LRDP shall be held by the Commission not later than sixty (60) days following the day on which the LCP or LRDP was properly submitted. All dates for public hearing shall be set with a view toward allowing thorough public dissemination of the information contained in the LCP or LRDP prior to the time of the hearing, and toward allowing full public participation and attendance at the meeting. If a land use plan and implementing actions are combined in a total LCP, then the deadline for commission action on the land use plan phase shall apply to commission review of the total LCP.
Cal. Code Regs. Tit. 14, § 13522
Note: Authority cited: Section 30501, Public Resources Code. Reference: Sections 30500 and 30511, Public Resources Code.