The executive director of the commission shall not be deemed to have received the notice of permit issuance from the local government unless the notice form is completed and the permit on its face includes the findings required by Section 13311 and the project description set forth in the application for which the permit has been issued. If the executive director determines that the notice cannot be received, it shall be returned to the local government within five (5) working days of its submission for completion and appropriate adjustment of the 20 working day effective period statement required by Section 13313. A properly completed notice shall be received by the executive director of the commission and stamped with the date of receipt.
Cal. Code Regs. Tit. 14, § 13316
2. Amendment filed 8-2-89; operative 9-1-89 (Register 89, No. 32).
Note: Authority cited: Sections 30333 and 30620, Public Resources Code. Reference: Sections 30600, 30602, 30604 and 30620.5, Public Resources Code.
2. Amendment filed 8-2-89; operative 9-1-89 (Register 89, No. 32).