Cal. Code Regs. tit. 14 § 2630

Current through Register 2024 Notice Reg. No. 49, December 6, 2024
Section 2630 - Survey Application Processing Time
(a) Within fifteen (15) calendar days from the receipt of the survey application and alternative methodology procedure, if applicable, from an operator of a dropoff or collection program requesting approval to use the Division's methodology or an alternative methodology to determine their program's specific individual commingled rate, the Division shall inform the applicant, in writing, that the survey application and alternative methodology procedure, if applicable, are either complete and accepted for processing, or incomplete. If the survey application and/or alternative methodology procedure, if applicable, are incomplete, the Division shall indicate, in writing, to the applicant what information or documentation is required. The applicant shall submit the required additional information or documentation, to the Division, no later than ten (10) calendar days from the date indicated in the Division's letter requesting additional information or documentation. Material submitted later than ten (10) calendar days will be rejected and the application will be denied.
(b) Within fifteen (15) calendar days after the Division informs the applicant of the receipt of a complete survey application and alternative methodology procedure, if applicable, as indicated in subsection 2630(a) above, the Division shall approve or disapprove the survey application and alternative methodology procedure, if applicable.
(c) If the application is disapproved, the applicant may request an appeal pursuant to subsection 2645 of these regulations.
(d) The applicant may begin using the approved survey methodology for the specified survey period, after receiving written notification from the Division that the survey application and alternative methodology procedure, if applicable, has been approved.

Cal. Code Regs. Tit. 14, § 2630

1. New section filed 10-27-94 as an emergency; operative 10-27-94 (Register 94, No. 43). A Certificate of Compliance must be transmitted to OAL by 2-24-95 or emergency language will be repealed by operation of law on the following day.
2. Certificate of Compliance as to 10-27-94 order including amendment of section and NOTE transmitted to OAL 2-24-95 and filed 4-7-95 (Register 95, No. 14).
3. Editorial correction of NOTE (Register 96, No. 10).
4. Amendment of section heading and subsections (a), (b) and (d) filed 1-26-2001; operative 1-26-2001 pursuant to Government Code section 11343.4(c) (Register 2001, No. 4).
5. Amendment of subsection (a) and NOTE filed 3-4-2009; operative 4-3-2009 (Register 2009, No. 10).

Note: Authority cited: Sections 14530.5(b) and 14536(b), Public Resources Code. Reference: Section 14511.7 and 14552(a), Public Resources Code.

1. New section filed 10-27-94 as an emergency; operative 10-27-94 (Register 94, No. 43). A Certificate of Compliance must be transmitted to OAL by 2-24-95 or emergency language will be repealed by operation of law on the following day.
2. Certificate of Compliance as to 10-27-94 order including amendment of section and Notetransmitted to OAL 2-24-95 and filed 4-7-95 (Register 95, No. 14).
3. Editorial correction of Note(Register 96, No. 10).
4. Amendment of section heading and subsections (a), (b) and (d) filed 1-26-2001; operative 1-26-2001 pursuant to Government Code section 11343.4(c) (Register 2001, No. 4).
5. Amendment of subsection (a) and Note filed 3-4-2009; operative 4-3-2009 (Register 2009, No. 10).