Cal. Code Regs. tit. 14 § 921.2

Current through Register 2024 Notice Reg. No. 45, November 8, 2024
Section 921.2 - Exemptions from Timber Harvesting Plan Requirements

To ensure that the protection necessary to maintain the integrity of Coastal Commission Special Treatment Areas is achieved, the following requirements shall apply to the Timber Operations exempt from filing of Timber Harvesting Plans under 14 CCR § 1038.

(a) The requirements of 14 CCR § 921.1(a) and (b) shall apply with the exception that, at the discretion of the Director, an initial inspection may not be required. Harvesting of Christmas trees are exempt from timber Marking requirements.
(b) The Director shall acknowledge in writing, and within 10 days, acceptance or rejection of the notice of Timber Operations. Timber Operations shall not commence until the Director's acceptance has been received by the Person who filed the notice.
(c) The requirements of PRC § 4585, Completion Report, and PRC § 4587, Stocking Reports, shall apply to exempt operations within the Coastal Commission Special Treatment Areas.

Cal. Code Regs. Tit. 14, § 921.2

1. New NOTE filed 8-10-83; effective upon filing pursuant to Government Code Section 11346.2(d) (Register 83, No. 37).
2. Amendment filed 11-15-85; effective thirtieth day thereafter (Register 85, No. 46).
3. Change without regulatory effect amending section filed 10-31-2017 pursuant to section 100, title 1, California Code of Regulations (Register 2017, No. 44).

Note: Authority cited: Sections 4551 and 4553, Public Resources Code. Reference: Sections 4551.5 and 30417, Public Resources Code.

1. New NOTE filed 8-10-83; effective upon filing pursuant to Government Code Section 11346.2(d) (Register 83, No. 37).
2. Amendment filed 11-15-85; effective thirtieth day thereafter (Register 85, No. 46).
3. Change without regulatory effect amending section filed 10-31-2017 pursuant to section 100, title 1, California Code of Regulations (Register 2017, No. 44).