Section R7-2-1144 - Stay of Procurements During the Protest

The district representative may stay all or part of the procurement or contract if it is determined that there is a reasonable probability the protest will be upheld or that a stay is advantageous to the school district. The district representative shall notify the successful contractor if award has been made or, if no award has been made, all interested parties of the stay in writing no later than the time of issuance of the district representative's decision in accordance with R7-2-1145.

Ariz. Admin. Code § R7-2-1144

Adopted effective December 17, 1987 (Supp. 87-4). Amended by exempt rulemaking at 33 A.A.R. 1527, effective 7/1/2014. Amended by final exempt rulemaking at 26 A.A.R. 597, effective 7/1/2020.