Ariz. Admin. Code § 7-2-1005

Current through Register Vol. 31, No. 2, January 10, 2025
Section R7-2-1005 - Change Orders and Contract Modifications

Any change order or contract modification that exceeds $100,000 or five percent, whichever is greater, may be executed only if the governing board determines in writing that the change order or contract modification is advantageous to the school district and the price is determined to be fair and reasonable.

Ariz. Admin. Code § R7-2-1005

Adopted effective December 17, 1987 (Supp. 87-4). Amended by exempt rulemaking at 33 A.A.R. 1525, effective 7/1/2014.