Current through Register Vol. 31, No. 2, January 10, 2025
Section R2-7-704 - Refusal to Submit Cost or Pricing DataA. If an offeror fails to submit cost or pricing data in the required form and within the time-frames required, the agency chief procurement officer may reject the offer.B. If a contractor fails to submit data to support a contract modification in the form required and within the time-frames required, the agency chief procurement officer may: 1. Reject the contract modification; or2. Set the amount of the contract modification subject to the contractor's rights under Article 9 of the Arizona Procurement Code. Ariz. Admin. Code § R2-7-704
New Section made by final rulemaking at 12 A.A.R. 508, effective April 8, 2006 (Supp. 06-1).