Ariz. Admin. Code § 2-7-509

Current through Register Vol. 31, No. 2, January 10, 2025
Section R2-7-509 - Conditions for Use of Substitute Security in Lieu of Retention

A contractor may submit substitute security to replace contract payment retention if:

1. The contractor requests the use of substitute security before the first progress payment;
2. The contractor submits an invoice with each progress payment in an amount of no less than 10% of the progress payment, or the contractor submits an invoice once at the beginning of the project in an amount no less than 5% of the total contract amount;
3. The interest earned on the security shall accrue to the benefit of the contractor but shall be retained by the contractor until the agency chief procurement officer has approved completion and acceptance of all work to be performed under the contract; and
4. The contractor ensures that the date of maturity of the security is after the estimated contract completion date, but no later than one year after the estimated contract completion date.

Ariz. Admin. Code § R2-7-509

Adopted as an emergency effective January 1, 1985, pursuant to A.R.S. § 41-1003, valid for only 90 days (Supp. 84-6). Emergency expired. Permanent rule adopted effective April 3, 1985 (Supp. 85-2). Amended effective April 2, 1993 (Supp. 93-2). Section repealed; new Section made by final rulemaking at 12 A.A.R. 508, effective April 8, 2006 (Supp. 06-1).