Current through Register Vol. 30, No. 43, October 25, 2024
Section R18-2-1413 - Criteria and Procedures: Timely Implementation of TCMsA. During all periods the transportation plan, TIP, or FHWA, or FTA project which is not from a conforming plan and TIP shall provide for the timely implementation of TCMs from the applicable implementation plan.B. For transportation plans, this criterion is satisfied if the following two conditions are met:1. The transportation plan, in describing the envisioned future transportation system, provides for the timely completion or implementation of all TCMs in the applicable implementation plan which are eligible for funding under 23 U.S.C. or the Federal Transit Act, consistent with schedules included in the applicable implementation plan.2. Nothing in the transportation plan interferes with the implementation of any TCM in the applicable implementation plan.C. For TIPs, this criterion is satisfied if all of the following conditions are met:1. An examination of the specific steps and funding source needed to fully implement each TCM indicates that TCMs which are eligible for funding under 23 U.S.C. or the Federal Transit Act are on or ahead of the schedule established in the applicable implementation plan, or, if such TCMs are behind the schedule established in the applicable implementation plan, the MPO and USDOT have determined that past obstacles to implementation of the TCMs have been identified and have been or are being overcome, and that all state and local agencies with influence over approvals or funding for TCMs are giving maximum priority to approval or funding of TCMs over other projects within their control, including projects in locations outside the nonattainment or maintenance area. Maximum priority to approval or funding of TCMs includes demonstrations with respect to funding acceleration, commitment of staff or other agency resources, diligent efforts to seek approvals, and similar actions.2. If federal funding intended for TCMs in the applicable implementation plan has previously been programmed but is reallocated to projects in the TIP other than TCMs, (or if there are no other TCMs in the TIP, to projects in the TIP other than projects which are eligible for federal funding under ISTEA's Congestion Mitigation and Air Quality Improvement Program), and the TCMs are behind the schedule in the implementation plan, the TIP cannot be found to conform.3. Nothing in the TIP may interfere with the implementation of any TCM in the applicable implementation plan.D. For FHWA or FTA projects which are not from a conforming transportation plan and TIP, this criterion is satisfied if the project does not interfere with the implementation of any TCM in the applicable implementation plan.Ariz. Admin. Code § R18-2-1413
Adopted effective June 15, 1995 (Supp. 95-2).