Public Water System Design Review Application Types | Fees1, 2 |
Approval to Construct Public Water Supply Distribution System: | |
* 150 or fewer service connections | $1,284 |
* 151 to 300 service connections | $1,998 |
* 301 to 450 service connections | $2,711 |
* 451 to 600 service connections | $3,425 |
* 601 to 750 service connections | $4,138 |
* Each additional 150 service connections | Add $714 |
Water Treatment Plants and Blending Plans (including new source approval if applicable): | |
* < 0.1 mgd | $2,141 |
* >= 0.1 mgd and < 1 mgd | $2,854 |
* >= 1 mgd and < 5 mgd | $4,281 |
* >= 5 mgd | $7,135 |
Well (including new source approval if applicable) | $1,784 |
Storage Tank | $1,142 |
Booster Pump | $1,142 |
Main Line Extension | $357 |
Chlorinators/Disinfection Devices | $357 |
Extension of Time to Construct3 | 50% of the application fee, not to exceed $714 |
Priority Review Fee4 | Double the Standard Fee |
1 Fees are calculated on a per-unit basis; i.e., a separate fee is assessed for each separate storage tank, booster pump, disinfection device, or main line extension.
2 Fees for each application type are cumulative; an applicant must pay the total of all pertinent fees.
3 Extensions of time to construct are issued pursuant to A.A.C. R18-5-505(E); the Section states that an Approval to Construct becomes void if construction is not commenced or completed within a specified time period, unless the Department grants an extension of time.
4 Priority Review Projects require Department authorization prior to filing.
Ariz. Admin. Code tit. 18, ch. 14, art. 2, tbl. 1