Ariz. Admin. Code § 18-13-1606

Current through Register Vol. 30, No. 24, June 14, 2024
Section R18-13-1606 - Fees

In accordance with A.R.S. §§ 49-855(C)(2) and 49-863, the treatment, storage, or disposal facility in this state that first receives a shipment of PCS shall remit to the Department a fee of $4.50 per ton but not more than $45,000 per generator site per year for PCS that is transported to the facility.

Ariz. Admin. Code § R18-13-1606

Recodified from R18-8-1606 at 8 A.A.R. 5172, effective November 27, 2002 (Supp. 02-4). Amended by final rulemaking at 18 A.A.R. 1217, effective July 1, 2012 (Supp. 12-2).