Ariz. Admin. Code § 14-5-109

Current through Register Vol. 30, No. 25, June 21, 2024
Section R14-5-109 - Industrial Track Standards
A. This Section shall be applicable to all industrial track construction, reconstruction, and repair commencing after the effective date of this Section.
1. The industry and the railroad contractor shall be responsible for notifying the Commission in writing prior to the construction, reconstruction, or alteration of industrial track, structures, or facilities adjacent thereto.
2. The proposed design plans of any construction, reconstruction, or alteration of industrial track shall be submitted to the Commission, Railroad Safety Section, Phoenix, Arizona, prior to any construction, reconstruction, or alteration of industrial track.
B. The following construction standards shall apply for all industrial track:
1. Profile:
a. Maximum grade of any proposed track, as shown on any plan, shall be 2% and shall not be exceeded. At all locations, excessive grades and frequent changes of grade shall be avoided. Where grade line changes, appropriate vertical curves shall be installed.
b. In cut sections, grade line shall be uniform throughout the cut to facilitate proper drainage. Grades in cuts shall not be less than 3/10% and not more than 1%.
2. Subgrade:
a. Where soil condition, drainage conditions or amount of traffic justify, the upper portion of the subgrade shall be designed to provide adequate support. Methods of increasing support shall be to provide select material to an adequate supporting depth over the existing subgrade or subgrade stabilization.
b. The depth of any proposed material shall be specified by the design plans.
c. The upper portion of any subgrade to be stabilized shall be stabilized by thoroughly mixing suitable chemical additives such as cement, fly ash, or lime with the soil before compaction.
d. Each layer shall be fully compacted by approved mechanical compacting equipment before the next layer is placed. A fully compacted layer shall have a dry density of at least 95% of the maximum dry density.
e. Type of soil and soil conditions shall be indicated on any proposed plans along with typical sections showing rail, tie ballast, subballast, and any other appurtenances.
3. Drainage:
a. Each drainage or other water-carrying facility under or immediately adjacent to the roadbed shall be maintained and kept free of obstruction to accommodate expected water flow for the area concerned.
b. Every effort shall be made to keep the tracks, roadbed, and walkways properly drained at all times.
4. Ballast:
a. Ballast material shall conform to the recommended specifications contained in the American Railroad Engineering Association "Manual for Railway Engineering" (AREA Manual), as amended and revised through July 31, 1990, incorporated herein by reference, on file with the office of the Secretary of State, and copies available from the American Railroad Engineering Association, 50 F Street NW, Washington, D.C. 20001. The gradation of a ballast material shall be a prime consideration in track performance of ballast materials. Ballast material used in industrial tracks shall be not less than 3/4 of an inch to 1 1/2 inches, pursuant to AREA No. 4 gradation in the AREA Manual.
b. Ballast material may be crushed rock, slag, or equally stable material that will provide uniform support to the ties, will drain properly, and is not chemically reactive. The material used for ballast shall not short track signals. Quarried stone or slag produced in a crushing-screening plant shall be preferred when it satisfies all of the following specifications:
i. A shrinkage factor of 12% to 15% in volume differential from loose to compacted state.
ii. Processed ballast shall be composed of hard, strong, and durable particles free from excessive amounts of deleterious substances.
iii. Deleterious substances shall not be present in processed ballast in excess of the following amounts:
(1) Soft and friable pieces--5%;
(2) Material finer than No. 200 sieve--1%;
(3) Clay lumps--1/2%.
iv. Percentage of wear of processed ballast, tested in the Los Angeles machine, shall not be greater than 40%.
v. Soundness of processed ballast for use in regions where freezing temperatures are expected shall be such that when tested in the sodium sulfate soundness test, the weighted average loss shall be not in excess of 7% after five cycles.
vi. Compacted weight of ballast shall be not less than 70 pounds per cubic foot for blast furnace-slag and 90 pounds per cubic foot for all other slags and crushed rock products.
vii. Flat or elongated particles, particles with length three times greater than average thickness, shall not exceed 5% by weight in the ballast.
c. Prior to installation, the supplier shall provide the railroad or industrial track owner with certified test results of ballast quality and grading.
d. Care shall be used to ensure even distribution of ballast in the track. A minimum ballast depth of 8 inches below the ties shall be acceptable as a subballast base. Ballast shall be inserted under ties in convenient lifts but under not less than two lifts. Proper cross level, line and grade shall be attained on the final lift in accordance with currently accepted practice.
e. Top of track ballast shall be dressed parallel with top of rails to a depth of 1 inch below top of tie extending 6 inches beyond end of tie. Ballast shall be thoroughly tamped for each tie end to 15 inches inside of rail. Centers shall be filled but not tamped. All work of track laying and surfacing shall be of the highest quality in accordance with currently accepted practice.
f. Each owner of the track to which the ballast standards apply shall maintain proper track cross level, surface, and alignment prescribed as follows:
i. The runoff in any 31 feet of rail at the end of a rise may be not more than 3 1/2 inches.
ii. The deviation from uniform profile on either rail at the mid-ordinate of a 62-foot chord may be not more than 3 inches.
iii. Deviation from designated elevation on spirals may be not more than 1 3/4 inches.
iv. Variation in cross level on spirals in any 31 feet may be not more than 2 inches.
v. Deviation from zero cross level at any point on tangent or from designated elevation on curves between spirals may be not more than 3 inches.
vi. The difference in cross level between any two points less than 62 feet apart on tangents and curves between spirals may be not more than 3 inches.
vii. Alignment may not deviate from mid-ordinate of a 62-foot chord more than 3 inches.
5. The material, preservative treatment, quality control, inspection, and miscellaneous requirements for timber crossties and switch ties shall conform with the recommendations of Chapter 3, "Ties and Wood Preservation" of the AREA Manual and all of the following:
a. Crossties shall be either hardwood or softwood in accordance with the requirements of this Section.
b. Wooden crossties shall be new and manufactured from the following kinds of wood: Douglas fir, red oak, white oak, cypress, southern and western pine, elm, hickory, gum, or hemlock.
c. All wooden ties shall be made from sound, straight live timber and shall be free from any defects that may impair their strength and durability, such as bark, decay, splits, shakes, large or numerous holes or knots, pitch seams, pitch rings, grain with slant greater than 1 in 15, or other imperfections.
d. All crossties shall be a minimum of 8 feet in length. Ties shall measure 6 inches thick by 8 inches wide on top, AREA No. 6 grade. If a 6-inch wide base rail is used, 7-inch by 9-inch ties shall be required. All crossties shall be branded with the seller's symbol to indicate line end.
e. Crossties shall be spaced a maximum of 24 inches center to center. Each 39 feet of track shall be supported by a minimum of 19 crossties. The center of the ties shall coincide with the centerline of the track and the ties shall be laid at right angles to the rail with the wide-face up.
f. Hardwood ties shall be used on all curves of 2 degrees and over. Softwood ties shall be permitted on other curves and tangents.
g. Ties shall be inspected at suitable and convenient places satisfactory to the railroad or industry owner. Inspection shall include a reasonably close examination of the top, bottom, sides, and ends of each tie. All ties shall be judged independently using the following standards:
i. Decay shall be the disintegration of the wood substance due to the actions of wood destroying fungi. "Blue Stain" is decay and shall be permissible in all wood.
ii. A large hole shall be more than 1/2 inch in diameter and 3 inches deep within, or more than 1/4 the width of the surface on which it appears and 3 inches deep outside, the sections of the tie between 20 inches and 40 inches from its middle. Numerous holes shall be any number equaling a large hole in damaging effect. Such holes may be caused in manufacture or otherwise.
iii. Within the rail bearing areas, a large knot shall be one having an average diameter more than 1/3 the width of the surface on which it appears; but such a knot shall be allowed if it is located outside the rail-bearing areas. Numerous knots shall be any number equaling a large knot in damaging effect.
iv. A shake shall be a separation along the grain, most of which occurs between the rings of annual growth.
v. A split shall be a separation of the wood extending from one surface to an opposite or adjacent surface. In unseasoned crossties, a split no more than 1/8 of an inch wide or 4 inches long shall be acceptable. In a seasoned crosstie, a split no more than 1/4 of an inch wide or longer than the width of the face across which it occurs shall be acceptable. In seasoned crossties, a split exceeding the limit shall be acceptable provided split limitations and anti-splitting devices are approved by the buyer and properly applied.
vi. Except in woods with interlocking grain, a slant in grain in excess of 1 inch in 15 inches shall be rejected.
vii. In manufacture:
(1) A tie shall be considered straight:
(a) When a straight line along the top from the middle of one end to the middle of the other end is entirely within the tie; and
(b) When a straight line along a side from the middle of one end to the middle of the other end is anywhere more than 2 inches from the top and the bottom of the tie.
(2) The top and bottom of a tie shall be considered parallel if any difference in the thicknesses at the sides or ends does not exceed 1/8 of an inch.
viii. The lengths, thicknesses, and widths specified shall be minimum for the standard sizes. Ties over 1 inch longer, thicker, or wider than the standard size ordered shall be rejected.
ix. A bark seam or pocket shall be a patch of bark partially or wholly enclosed in the wood. Bark seams shall be allowed provided they are not more than 2 inches below the surface or 10 inches long.
x. Ties with continuous checks appearing on one face only, whose depth in a fully seasoned tie is greater than 1/4 the thickness and longer than 1/2 the length shall be rejected.
h. The maximum distance between non-defective timber crossties shall be 70 inches, center of tie to center of tie.
i. A timber crosstie shall be considered defective when it is all of the following:
i. Broken through;
ii. Split or otherwise impaired to the extent that it will not hold spikes or will allow ballast to work through;
iii. So deteriorated that the tie-plate can move laterally more than 1/2 of an inch relative to the crossties;
iv. Cut by the tie-plate through more than 40% of its thickness; and
v. Not spiked as required by this Section.
j. Industry track shall have at least one non-defective crosstie whose centerline is within 18 inches of the rail joint location.
k. Used crossties, although not recommended, may be used subject to prior approval from the Commission.
l. Treated tie plugs of proper size shall be used to fill holes tightly and driven into old spike holes of used ties. Approved granular tie plug material may be used in lieu of treated tie plugs.
6. Switch ties:
a. Switch ties shall be new and shall be hardwood in accordance with the requirements of this Section. Switch ties shall be located as shown on the turnout plans.
b. All switch ties shall be 7 inches thick by 9 inches wide in cross section. Switch tie length shall be as indicated on the turnout plans in 1 foot increments.
c. All switch ties shall be sawed top, bottom and sides, cut square at the ends, have top and bottom parallel, and have bark entirely removed.
7. Tie plates:
a. Tie plates shall be placed under each rail at every tie. The tie plates shall be placed with the shoulder squarely against the rail.
b. No crooked tie plates shall be permitted. Each tie plate shall be of proper design to fit the rail section being used.
8. Rail:
a. All rail used in industrial track construction shall weigh a minimum of 90 pounds per yard. The majority of rails used shall be a minimum of 30 feet in length, with no more than 20% of varying lengths down to 24 feet, except as required in switches.
b. Rail shall be laid with joints staggered so that joints on one side will not be more than 4 feet from center of the opposite rail. The best running side of the relay railhead shall form the gage side of the rail as laid.
c. Rails shall be new or equal to No. 2 relay rail or No. 3 relay rail as per the AREA Manual recommendations for rail grading classifications. Overflow on one or both sides shall be less than 1/4 of an inch. Base shall be solid and free of visual defects with only minor pitting. Relay rail shall be considered to be used material.
d. The bottom of rail, tie plate, and top surface of tie shall be clean and smooth to provide for full bearing for rails and tie plates.
e. The use of a torch for cutting track rail, except for field welds or for burning bolt holes shall be prohibited. A rail saw or rail chisel properly and expertly used for cutting and a hand or power rail drill for boring holes shall be employed. All chips and burrs shall be removed and all drilled holes shall be peened. The bolt hole shall conform to the standard plans.
f. Angle bars of approved design shall be properly fitted against the rail and properly bolted. Each joint shall be bolted with at least two bolts through each rail end. Joint bars cracked or broken through between the middle two bolts shall be replaced. Compromise and insulated joint bars of proper design shall be used where rail size and conditions dictate. Track bolts, of proper size, fitted with approved spring washers, shall be fully tightened to proper tension.
9. Spiking:
a. Each rail will be spiked with two spikes per tie plate on tangent track, staggered with inside spikes to the east or north, outside spikes to the west or south.
b. Spikes shall be 5/8 of an inch wide by 6 inches long.
c. Track spikes shall be started and driven vertically with face shank in contact with the rail so that the face of the spike shall have full hold on rail base. Damage to tie timber fiber shall be minimized.
d. Spikes shall not be struck after head is down to snug contact with the railbase. Care shall be taken not to overdrive spikes and rail shall not be gouged or struck with spike maul or other tool.
e. In the construction of road crossings and turnouts, line spikes and hold down or anchor spikes shall also be used throughout the crossing and turnout closure rails. Hold down or anchor spikes shall be used on curves of 5 degrees or more.
10. Gage:
a. Gage is measured between the heads of the rails at right angles to the rails in a plane 5/8 of an inch below the top of the railhead.
b. In new industrial construction the rails shall be gaged to 4 feet 8 1/2 inches.
c. Rail gage shall be maintained at not less than 4 feet 8 inches, nor more than 4 feet 9 3/4 inches for both curved and tangent track.
11. Rail anchors:
a. 16 anchors per 39 feet of track shall be used, and 4 nonconsecutive ties shall be box-anchored per rail.
b. Anchors shall be used throughout the turnout area. The same tie shall be box-anchored across.
c. Anchors shall not be placed on joint ties or ties adjacent to joint ties.
d. Additional anchors shall be applied where longitudinal rail movement needs to be effectively controlled.
12. Gage rods:
a. Gage rods may be used on curves where it is difficult to maintain gage.
b. On curves between 7 degrees and 10 degrees, 4 gage rods per 39-foot panel shall be installed and on curves between 10 degrees and 12 degrees, 5 gage rods per 39-foot panels shall be installed.
13. Switches:
a. Each stock rail shall be securely seated in switch plates, but care shall be taken to avoid canting the rail by overtightening the rail braces.
b. Each switch point shall fit its stock rail properly, with the switch stand in either of its closed positions to allow wheels to pass the switch point. Lateral and vertical movement of a stock rail in the switch plates or of a switch plate on a tie shall not adversely affect the fit of the switch point to the stock rail.
c. Each switch shall be maintained so that the outer edge of the wheel tread cannot contact the gage side of the stock rail.
d. The heel of each switch rail shall be secure and the bolts in each heel shall be kept tight.
e. Each switch stand and connecting rod shall be securely fastened and operable without excessive lost motion.
f. Unusually chipped or worn switch points shall be repaired or replaced. Metal flow shall be removed to ensure proper closure.
g. The railroad shall be responsible for the installation and maintenance of switches connecting industrial track to railroad track facilities.
h. Owners of industrial switches shall be responsible for the installation and maintenance of their switches.
i. "Run-through" or damaged switches shall be repaired immediately.
14. Derails:
a. Derails shall be installed where grade or other conditions indicate the need.
b. Derails shall be installed so that derailed cars will not foul or damage adjacent track or railroad structures.
c. Derail signs shall be clearly visible.
d. When in a locked position, the derail shall be free of lost motion which will allow it to be operated without removing the lock.
15. Car stops or bumping posts:
a. Car stops or bumping posts shall be installed at the end of all industry spur tracks.
b. Car stops or bumping posts may be of any design that will adequately stop a car without damaging the car, such as, "wheelstops", "drawbar stop", or "earth-tie stop".

Ariz. Admin. Code § R14-5-109

Adopted effective May 28, 1992 (Supp. 92-2).