Ariz. Admin. Code § 14-2-2626

Current through Register Vol. 30, No. 25, June 21, 2024
Section R14-2-2626 - Utility Reporting Requirements
A. Each Utility shall maintain records concerning each received Application for Interconnection and shall include in its records:
1. The date the Application was received;
2. Any documents generated in the course of processing the Application;
3. Any correspondence regarding the Application;
4. The final disposition of the Application; and
5. The final disposition date.
B. By March 30 of each year, each Utility shall file with the Commission a Distributed Generation Interconnection Report, with data for the preceding calendar year that shall include:
1. The number of complete Applications denied by track level, including the reasons for denial;
2. A list of special contracts, approved by the Commission during the reporting period, that provide discounted rates to Customers as an alternative to self-generation;
3. Pre-Application Report:
a. Total number of reports requested;
b. Total number of reports issued;
c. Total number of requests withdrawn; and
d. Maximum, mean, and median processing times from receipt of request to issuance of report;
4. Interconnection Application:
a. Total number received, broken down by:
i. Primary fuel type (e.g., solar, wind, biogas, etc.); and
ii. System size (<20 kW, 20 kW-2 MW, >2MW);
b. Expedited Interconnection Process:
i. Total number of applications approved;
ii. Total number of applications denied;
iii. Total number of applications withdrawn; and
iv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement;
c. Level 1 Super Fast Track Process:
i. Total number of applications approved;
ii. Total number of applications denied;
iii. Total number of applications withdrawn; and
iv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement;
d. Level 2 Fast Track Process:
i. Total number of applications approved;
ii. Total number of applications denied;
iii. Total number of applications withdrawn; and
iv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement;
e. Supplemental Review:
i. Total number of applications approved;
ii. Total number of applications denied;
iii. Total number of applications withdrawn; and
iv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement; and
f. Level 3 Study Process:
i. Total number of System Impact Studies completed;
ii. Maximum, mean, and median processing times from receipt of signed System Impact Study agreement to provision of study results;
iii. Total number of Facilities Studies completed;
iv. Maximum, mean, and median processing times from receipt of signed Facility Study agreement to provision of study results;
v. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement.

Ariz. Admin. Code § R14-2-2626

Adopted by final rulemaking at 26 A.A.R. 473, effective 2/25/2020.