Current through Register Vol. 30, No. 25, June 21, 2024
Section R14-2-2626 - Utility Reporting RequirementsA. Each Utility shall maintain records concerning each received Application for Interconnection and shall include in its records:1. The date the Application was received;2. Any documents generated in the course of processing the Application;3. Any correspondence regarding the Application;4. The final disposition of the Application; and5. The final disposition date.B. By March 30 of each year, each Utility shall file with the Commission a Distributed Generation Interconnection Report, with data for the preceding calendar year that shall include: 1. The number of complete Applications denied by track level, including the reasons for denial;2. A list of special contracts, approved by the Commission during the reporting period, that provide discounted rates to Customers as an alternative to self-generation;3. Pre-Application Report: a. Total number of reports requested;b. Total number of reports issued;c. Total number of requests withdrawn; andd. Maximum, mean, and median processing times from receipt of request to issuance of report;4. Interconnection Application:a. Total number received, broken down by:i. Primary fuel type (e.g., solar, wind, biogas, etc.); and ii. System size (<20 kW, 20 kW-2 MW, >2MW);b. Expedited Interconnection Process:i. Total number of applications approved;ii. Total number of applications denied;iii. Total number of applications withdrawn; andiv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement;c. Level 1 Super Fast Track Process:i. Total number of applications approved;ii. Total number of applications denied;iii. Total number of applications withdrawn; andiv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement;d. Level 2 Fast Track Process:i. Total number of applications approved;ii. Total number of applications denied;iii. Total number of applications withdrawn; andiv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement;e. Supplemental Review:i. Total number of applications approved;ii. Total number of applications denied;iii. Total number of applications withdrawn; andiv. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement; andf. Level 3 Study Process:i. Total number of System Impact Studies completed;ii. Maximum, mean, and median processing times from receipt of signed System Impact Study agreement to provision of study results;iii. Total number of Facilities Studies completed;iv. Maximum, mean, and median processing times from receipt of signed Facility Study agreement to provision of study results;v. Maximum, mean, and median processing times from receipt of complete Application to execution of Interconnection Agreement.Ariz. Admin. Code § R14-2-2626
Adopted by final rulemaking at 26 A.A.R. 473, effective 2/25/2020.