3 Alaska Admin. Code § 52.650

Current through May 31, 2024
Section 3 AAC 52.650 - Processing of power cost equalization requests
(a) Within 45 days after a participating electric utility makes a complete request under 3 AAC 52.640 for an adjustment of its power cost equalization per kilowatt-hour, the commission by order will approve the filing, modify and approve it, or suspend it in whole or in part for further action. If the commission enters an order suspending a power cost equalization request only in part, the part that is not suspended takes effect at the end of the 45-day period.
(b) If the commission determines that a request for an adjustment of power cost equalization per kilowatt-hour should be suspended, the commission will, in its discretion, grant interim, refundable power cost equalization per kilowatt-hour.

3 AAC 52.650

Eff. 10/28/89, Register 112; am 9/11/2004, Register 171

Authority:AS 42.05.141

AS 42.05.151

AS 42.45.110

AS 42.45.130

AS 42.45.160

AS 42.45.170