3 Alaska Admin. Code § 46.400

Current through December 21, 2024
Section 3 AAC 46.400 - Waiver of regulatory notice period
(a) When an electric reliability organization includes in its tariff letter a request under 3 AAC 46.330(a)(7) for a tariff filing to take effect before the end of the regulatory notice period under 3 AAC 46.320(c), the burden of showing good cause for waiving the regulatory notice period must be borne by the filing electric reliability organization.
(b) In response to each request under (a) of this section, the commission may take one of the following actions:
(1) deny the request and require at least the regulatory notice period to expire before allowing the tariff filing to take effect;
(2) grant the requested effective date as proposed in the tariff letter;
(3) allow the tariff filing to take effect before the end of the regulatory notice period but later than the requested effective date proposed in the tariff letter; or
(4) pending a public hearing, suspend the operation of the tariff filing for a period not longer than that permitted under AS 42.05.175(i).
(c) The commission, on its own motion or for good cause shown, may waive regulatory notice and specify an effective date before the end of the regulatory notice period for a tariff filing filed to comply with an order of the commission.

3 AAC 46.400

Eff. 3/11/2022, Register 241, April 2022

Authority:AS 42.05.141

AS 42.05.151

AS 42.05.770