Section 2 AAC 12.933 - General design-build requirements
(a) The procurement officer may conduct a design-build procurement process only if the commissioner of transportation and public facilities determines in writing that it is advantageous to the state.
(b) When a design-build procurement process is used, the request for proposals must solicit a single price for both design and construction services. Nothing in this subsection prohibits a multi-step award process.
(c) The provisions of 2 AAC 12.931 - 2 AAC 12.949 apply to, and are incorporated in, all design-build construction contracts entered by an agency.
(d) Design-build construction contracts must be procured
(1) in accordance with AS 36.30.200-36.30.265; and
(2) except as provided in 2 AAC 12.931 - 2 AAC 12.949, in accordance with 2 AAC 12.220 - 2 AAC 12.315 (Competitive Sealed Proposals); in the case of inconsistency with 2 AAC 12.220 - 2 AAC 12.315, the provisions of 2 AAC 12.931 - 2 AAC 12.949 control.

2 AAC 12.933

Eff. 8/21/2005, Register 175

Authority:AS 36.30.040

AS 36.30.200