Current through September 25, 2024
Section 18 AAC 75.420 - Procedures to apply for oil discharge prevention and contingency plans; plan renewals(a) A plan holder must apply for renewal of the department's approval of an oil discharge prevention and contingency plan in accordance with 18 AAC 75.408. For submittals after October 16, 2016, the application must be submitted at least 180 days, or the number of days stated in the plan approval letter under 18 AAC 75.460(a), in advance of expiration of the plan to permit department review before the plan approval expires.(e) An application for a plan renewal, including items that were not changed since the last plan approval, will be reviewed under the provisions of 18 AAC 75.455.Eff. 5/14/92, Register 122; am 11/27/2002, Register 164; am 4/16/2016, Register 218, July 2016; am 3/23/2017, Register 221, April 2017; am 10/27/2018, Register 228; am 2/5/2023, Register 245, April 2023Authority:AS 46.03.020
AS 46.04.030
AS 46.04.055
AS 46.04.070