18 Alaska Admin. Code § 75.410

Current through May 31, 2024
Section 18 AAC 75.410 - Procedures to apply for oil discharge prevention and contingency plans; new plans
(a) An application package for approval of a new oil discharge prevention and contingency plan must be submitted in accordance with 18 AAC 75.408. An application package must be submitted at least 180 days before the proposed start of operation.
(b) Repealed 4/16/2016.
(c) The department will review an application package for a new plan using the procedures set out under 18 AAC 75.455 and will issue its decision under 18 AAC 75.460(a).
(d) Repealed 4/16/2016.
(e) Repealed 4/16/2016.

18 AAC 75.410

Eff. 5/14/92, Register 122; am 11/27/2002, Register 164; am 4/8/2012, Register 202; am 4/16/2016, Register 218, July 2016; am 3/23/2017, Register 221, April 2017; am 10/27/2018, Register 228; am 2/5/2023, Register 245, April 2023

Authority:AS 46.03.020

AS 46.04.030

AS 46.04.055

AS 46.04.070