Current through October 17, 2024
Section 18 AAC 72.501 - Permit and operational requirementsA person who discharges wastewater into a conventional wastewater system must have
(1) a system that meets the requirements of this chapter;(2) a system that is documented in accordance with 18 AAC 72.550 or 18 AAC 72.560 if plan approval is not required;(3) written approval from the department, if plan approval is required under 18 AAC 72.515; and(4) a discharge permit from the department if a permit is required under 18 AAC 72-010.Eff. 10/1/2023, Register 247, October 2023Authority:AS 44.46.020
AS 46.03.020
AS 46.03.110