18 Alaska Admin. Code § 72.255

Current through May 31, 2024
Section 18 AAC 72.255 - Stabilization ponds
(a) Plans for construction of a stabilization pond must include
(1) the items required to be submitted under 18 AAC 72.245;
(2) criteria for dike design, materials, construction, and safety;
(3) methods and the location for disposal of non-piped wastewater, including truck-hauled waste and honey bucket disposal;
(4) a soils analysis and report meeting the criteria of 18 AAC 72.265;
(5) for nonpercolating stabilization ponds, a coefficient of permeability of the pond liner that does not exceed an equivalent percolation rate of 500 gallons per day per acre at a water depth of six feet; and
(6) for percolating stabilization ponds,
(A) hydrologic data and groundwater modeling demonstrating compliance with any permit issued under this chapter; and
(B) information demonstrating that the use of the stabilization pond will not interfere with existing public and private drinking water sources.
(b) To obtain an approval to operate a stabilization pond, the applicant shall submit to the department items required under 18 AAC 72.240.

18 AAC 72.255

Eff. 4/1/99, Register 149; am 10/1/2023, Register 247, October 2023

Authority:AS 44.46.020

AS 46.03.010

AS 46.03.020

AS 46.03.050

AS 46.03.100

AS 46.03.110