18 Alaska Admin. Code § 50.302

Current through May 31, 2024
Section 18 AAC 50.302 - Construction permits
(a) An owner or operator must obtain a construction permit before beginning actual construction of a new major stationary source, a major modification, a PAL major modification, or a new stationary source or modification subject to the construction permitting requirements of 42 U.S.C. 7412(i) (Clean Air Act sec. 112(i)). The owner or operator must obtain one or more of the following types of construction permits, as applicable:
(1) a prevention of significant deterioration (PSD) permit under 18 AAC 50.306;
(2) a nonattainment area major stationary source permit, under 18 AAC 50.311;
(3) a construction permit under 18 AAC 50.316 for a major source of hazardous air pollutants.
(b) If a stationary source or modification requires permits under more than one section in this chapter, the owner or operator may file a single permit application, and the department will issue a single permit incorporating all applicable construction permit requirements.
(c) If a term or condition is established in a PSD permit listed in (a)(1) of this section, or established in a PSD permit incorporated into a permit under (b) of this section, and is identified in the permit as solely necessary to meet a Title V requirement associated with an integrated review conducted under 18 AAC 50.306(c) (3), the term or condition is considered a Title V term or condition upon incorporation into a Title V permit. A subsequent revision to the term or condition may be made solely through the applicable Title V operating permit amendment or modification provisions of 18 AAC 50.326.

18 AAC 50.302

Eff. 10/1/2004, Register 171; am 12/9/2010, Register 196; am 9/14/2012, Register 203

Authority:AS 46.03.020

AS 46.14.010

AS 46.14.020

AS 46.14.030

AS 46.14.120

AS 46.14.140

Sec. 30, ch. 74,

SLA 1993