18 Alaska Admin. Code § 15.020

Current through May 31, 2024
Section 18 AAC 15.020 - Permit applications
(a) Except as provided in 18 AAC 15.130 - 18 AAC 15.140, an applicant for a permit or written approval subject to 18 AAC 15.020 - 18 AAC 15.100 must serve a complete application on the department.
(b) An applicant must serve a complete application under (a) of this section for the department's review at least
(1) five days before the proposed commencement of the operation, for applications for surface oiling permits;
(2) 30 days before the proposed commencement of construction, installation, modification, or improvement, for applications for plan approvals or permits for a sewerage system treatment works, or public water system;
(3) 60 days before the proposed commencement of construction, installation, modification, or improvement, for applications for plan approvals or permits for a municipal sewerage system, treatment works, or public water system project that involves state or federal monetary assistance;
(4) 60 days before the proposed commencement of the operation, for an application for a solid waste disposal permit, short-term variance form water quality standards, or wastewater disposal permit; and
(5) 100 days before the proposed commencement of a pesticide use that requires a permit under 18 AAC 90.

18 AAC 15.020

Eff. 11/25/77, Register 64; am 1/7/87, Register 100; am 8/2/90, Register 115; am 2/15/98, Register 145; am 7/11/2002, Register 163; am 4/10/2010, Register 194

Authority:AS 46.03.020

AS 46.03.100

AS 46.03.110

AS 46.03.320

AS 46.03.330

AS 46.03.720

AS 46.03.730