Current through October 17, 2024
Section 17 AAC 70.420 - Interport differential criteriaThe aggregate of the following cost criteria comprise the interport differential for a bid submitted by a shipyard facility:
(1) fuel to transport the vessel from its designated base port to the shipyard facility and return;(2) maintenance costs incurred and consumables used, including lubricants and other engine and deck stores, while transporting the vessel from its designated base port to the shipyard facility and return;(3) crew wages (A) to prepare the vessel for entry to the shipyard facility;(B) to deliver the vessel from its designated base port to the shipyard facility and return;(C) for crew that must travel to or from the vessel while it is in the shipyard facility; and(D) upon completion of the work, to prepare the vessel for revenue status;(4) nonwage costs to transport crew to or from the vessel while it is in the shipyard facility;(5) crew per diem while the vessel is in the shipyard facility;(6) travel costs and per diem for non-crew staff and consultants to administer the contract;(7) other interport costs not described in (1) - (6) of this section that relate to the performance of the maintenance or repair work of a vessel at a shipyard facility.Eff. 2/17/99, Register 149Authority:AS 36.30.015
AS 36.90.049
AS 44.42.020
AS 44.42.030