Section 17 AAC 42.318 - Nonresponsive bids

The airport manager shall reject a bid as nonresponsive if the bidder submits more than one bid under the same or different names or if the bid

(1) is submitted late or to the wrong place, unless the manager determines that the bid was received before the last date and time set for bid submission and that the delay or incorrect place of bid submission was due to an error of the department;
(2) does not include the required bid deposit;
(3) is not validly signed;
(4) is illegible;
(5) is not submitted in a sealed package;
(6) fails to acknowledge all material addenda the manager has issued;
(7) offers an alternative compensation formula that the invitation to bid does not allow;
(8) does not conform in all material respects to the invitation to bid; or
(9) is conditional.