Section 17 AAC 25.380 - Oversize and overweight vehicle permit fees
(a) The department will calculate a total permit fee from one or more of the following component fees, if applicable under (b) of this section:
(1) for a single move by a vehicle or load that is oversize only, other than a vehicle or load that is exempt under 17 AAC 25.012(b) (3), and except as provided in (5) of this subsection,
(A) the basic processing charge is $40;
(B) a surcharge will be added for excess width as follows, if applicable:
(i) for an overall width in excess of 10 feet and no more than 16 feet, $25;
(ii) for an overall width in excess of 16 feet, $35; and
(C) a surcharge will be added for excess height as follows, if applicable:
(i) for an overall height in excess of 16 feet and no more than 16.5 feet, $25;
(ii) for an overall height in excess of 16.5 feet, $35;
(2) for a single move by a vehicle or load operating between the Fox Weigh Station and Prudhoe Bay on the Dalton and Elliott Highways and that is oversize only under 17 AAC 25.012(a) and (b)(3), and except as provided in (5) of this subsection,
(A) the basic processing charge is $40;
(B) a surcharge will be added as set out in (1)(B) of this subsection for excess width, if applicable; and
(C) a surcharge will be added for excess height as follows, if applicable:
(i) for an overall height in excess of 17 feet and no more than 18.5 feet, $25;
(ii) for an overall height in excess of 18.5 feet, $35;
(3) for a single move by a vehicle or load that is overweight only, and except as provided in (5) of this subsection,
(A) the basic processing charge is $40; and
(B) a surcharge of $25 will be added if gross weight is 150,000 pounds or greater;
(4) for a single move by a vehicle or load that is oversize and overweight, and except as provided in (5) of this subsection,
(A) the basic processing charge is $70;
(B) a surcharge will be added as set out in (1)(B) of this subsection for excess width, if applicable;
(C) a surcharge will be added as set out in (1)(C) or (2)(C) of this subsection for excess height, if applicable; and
(D) a surcharge of $25 will be added if gross weight is 150,000 pounds or greater;
(5) for an oversize or overweight vehicle that requires the department's bridge design section review and approval to protect the public safety or the highway and its apparatus, a per-hour rate of $80;
(6) subject to the requirements for an extended use authorization under 17 AAC 25.320(c), and for an unlimited number of moves by a vehicle or load that is oversize, overweight, or both oversize and overweight during the period of
(A) no more than 30 days, the fee is
(i) $85 for a vehicle or load that is oversize only;
(ii) $85 for a vehicle or load that is overweight only; and
(iii) $165 for a vehicle or load that is both oversize and overweight;
(B) more than 30 days, but no more than 90 days, the fee is
(i) $220 for a vehicle or load that is oversize only;
(ii) $220 for a vehicle or load that is overweight only; and
(iii) $385 for a vehicle or load that is both oversize and overweight;
(C) more than 90 days, but no more than six months, the fee is
(i) $330 for a vehicle or load that is oversize only;
(ii) $330 for a vehicle or load that is overweight only; and
(iii) $605 for a vehicle or load that is both oversize and overweight;
(D) more than six months, but no more than nine months, the fee is
(i) $495 for a vehicle or load that is oversize only;
(ii) $495 for a vehicle or load that is overweight only; and
(iii) $935 for a vehicle or load that is both oversize and overweight;
(E) more than nine months, but no more than 12 months, the fee is
(i) $550 for a vehicle or load that is oversize only;
(ii) $550 for a vehicle or load that is overweight only; and
(iii) $1,100 for a vehicle or load that is both oversize and overweight.
(b) The department will calculate the total fee for a permit issued under 17 AAC 25.320 for oversize and overweight vehicles and loads as follows:
(1) for a single-trip permit for a single vehicle, the department will charge the applicable single move fee under (a)(1) - (5) of this section;
(2) for an extended-period permit for a single vehicle, the department will charge the applicable fee under (a)(6) of this section for an unlimited number of moves;
(3) repealed 11/16/2004;
(4) for a pre-issue single-trip permit, as described in section 3.2.1 of the department's Administrative Permit Manual: Oversize and Overweight Permits, as adopted by reference in 17 AAC 25.320(b), the department will charge the applicable single move fee under (a)(1) - (5) of this section;
(5) for an extended period permit, as described in section 3.2.2 of the department's Administrative Permit Manual: Oversize and Overweight Permits, as adopted by reference in 17 AAC 25.320(b), the department will charge the applicable fee under (a)(6) of this section for an unlimited number of moves;
(6) for a single-trip permit for a convoy, as described in section 3.2.1 and section 16 of the department's Administrative Permit Manual: Oversize and Overweight Permits, as adopted by reference in 17 AAC 25.320(b), the department will charge for each vehicle in the convoy the single move fee applicable to that vehicle under (a)(1) - (5) of this section; a convoy is eligible for a single-trip permit only;
(7) for equipment engaged in snow removal, the department will charge the applicable fee under (a)(6) of this section for an unlimited number of moves.
(c) The permit replacement fee is $30.
(d) The permit change fee for each change submitted is $30.
(e) The permit cancellation fee is $30 for each canceled permit. A permit may not be canceled after the permit expiration date.
(f) repealed 12/8/2018.

17 AAC 25.380

Eff. 10/7/2001, Register 160; am 11/16/2004, Register 172; am 4/9/2009, Register 190; am 4/12/2013; Register 206; am 2/10/2016, Register 217, April 2016; am 12/6/2018, Register 228, January 2019

Authority:AS 19.05.010

AS 19.05.020

AS 19.05.040

AS 19.10.060

AS 44.42.020

AS 44.42.030

AS 45.75.050