17 Alaska Admin. Code § 15.251

Current through May 31, 2024
Section 17 AAC 15.251 - Installation and inspection
(a) Each permittee shall give the department written notice not less than 10 days before the start of construction on any utility facility.
(b) A copy of the permit must be at the work site during construction and installation operations and must be shown, upon request, to any department representative, Alaska state trooper, or other enforcement officer of the state.
(c) The department will, in its discretion, require inspection of the facility during construction and installation operations. The inspection must be sufficient to ensure full compliance with the provisions of the permit.

17 AAC 15.251

Eff. 5/23/82, Register 82

Authority:AS 02.15.020

AS 02.15.102

AS 02.15.106

AS 19.05.020

AS 19.05.040

AS 19.25.200

AS 19.30.051

AS 19.30.121

AS 19.40.065

AS 35.05.020

AS 35.10.210

AS 35.10.230