Ala. Admin. Code r. 410-1-8-.08

Current through Register Vol. 43, No. 1, October 31, 2024
Section 410-1-8-.08 - Issuance Of Certificate Of Need
(1) The executive director of the state agency shall issue a certificate of need to the applicant thirty (30) days after the decision of the Certificate of Need Review Board is deemed final, unless the issuance of the certificate of need is suspended by the filing of a request for reconsideration pursuant to Sections 410-1-8-.14 and 410-1-8-.15, or request for fair hearing under Section 410-1-8 - .17. The 30 day period may be waived or extended with the consent of all parties. In cases where an Administrative Law Judge ("ALJ") the ALJ's proposed Findings of Fact and Conclusions of Law becomes the final decision of SHPDA due to no exceptions being filed, the Executive Director shall issue a certificate of need to the applicant within fifteen (15) days of such decision becoming final.
(2) A press release of the issuance of a Certificate of Need shall be issued the same day the certificate of need is issued to the applicant. The press release will include the following information:
(a) name of applicant;
(b) name and location of the project;
(c) description of the proposal; and
(d) the Certificate of Need Review Board's decision.

Ala. Admin. Code r. 410-1-8-.08

Amended: Filed September 19, 1996; effective October 23, 1996. Amended: Filed February 13, 1997; effective March 20, 1997.
Amended by Alabama Administrative Monthly Volume XXXIII, Issue No. 09, June 30, 2015, eff. 7/1/2015.

Author:

Statutory Authority:Code of Ala. 1975, § 22-21-265, 22-21-275(5).